Mbuu dam Desilting Project
Mbuu dam Desilting Project
The project is one out of ten projects in the Kilome Division Land Degradation Cluster in Makueni district in the Eastern Province of Kenya. The Kilome division land degradation cluster projects lie within about 40 square kilometres. All ten projects aim at reducing / preventing land degradation by focusing on the rehabilitation of gullies, water tanks for domestic and agricultural use, establishment of terraces and intercropping methods and reafforestation of catchment areas. The ten CBOs implementing the respective projects are supervised and coordinated by Kenya Initiatives for Development (KID) which has the role of a lead NGO.

This project plans to carry out the following activities:


? Purchase working tools of high quality - Oct. 1st -10th 2006.
? Mobilize tractor-Oct.1st -10th 2006.
? Desilt Mbuu dam - Oct. 15-25th 2006
? Construct manholes (inlet, outlet, inspection chamber) - Oct. 25th -Nov. 2006.


? Construct a masonry 20,000 litres tank in March 2007
? Construct cattle trough - April 2007.
? Construct water Kiosk - May 2007.
? Fence Mbuu dam - June 2007.


? Dig terraces in member?s farms Sept. - Oct. 2007 (CBO contribution).
? Plant 50 trees in each member?s farm in November2007


? Write and submit final project report to UNDP-GEF/SGP - January -March 2008.

 

Project Snapshot

Grantee:
Thome wa Kima Self Help Group
Country:
Kenya
Area Of Work:
Land Degradation
Grant Amount:
US$ 16,591.65
Co-Financing Cash:
Co-Financing in-Kind:
Project Number:
KEN-GEF-05-007
Status:
Satisfactorily Completed